Use this checklist to plan a FieldKo implementation from start to go-live. It’s written for implementation partners and the admins they work with. Each step links to the guide that explains it. Work through the guides in this order, and use each guide’s To confirm checks before you move on.
Phased plan of a FieldKo implementation in 9 stages: plan, prepare a sandbox, install and configure, set up users and access, load data, customize and integrate, test with pilot reps, go live in production, and hand over.Phased plan of a FieldKo implementation in 9 stages: plan, prepare a sandbox, install and configure, set up users and access, load data, customize and integrate, test with pilot reps, go live in production, and hand over.

The 9 stages of a FieldKo implementation.

User Permissions Needed

1. Plan

2. Prepare a Sandbox

3. Install and Configure

4. Set Up Users and Access

5. Load Data

6. Customize, Automate, and Integrate

7. Test with Pilot Reps

8. Go Live

9. Hand Over

Best Practice

Run a 90-Day Pilot

Before you roll out everywhere, prove a focused operating model in real stores: one business problem, a trusted baseline, a practical field workflow, and a written decision at each 30-day gate. Use this for a new rollout, a new region, or a major change to how visits, surveys, or exceptions work.
A 90-day pilot in 3 phases (understand and design, pilot in real conditions, stabilize and scale), each ending in a gate. Four stop signs, such as unreliable sync or no one accountable for exceptions, pause expansion.A 90-day pilot in 3 phases (understand and design, pilot in real conditions, stabilize and scale), each ending in a gate. Four stop signs, such as unreliable sync or no one accountable for exceptions, pause expansion.

The 90-Day Pilot: Phases, Gates, and Stop Signs

1

Days 1 to 30: Understand and Design

Interview and shadow reps, area managers, and commercial teams. Agree the business objective, pilot stores, and product scope. Write a short metric dictionary that defines in-stock, authorized, visited, and resolved, and record a baseline for 2 or 3 outcomes. Save the pilot stores as an account set.Gate: you have enough reliable information to design a focused pilot.
2

Days 31 to 60: Pilot in Real Conditions

Run a short standard visit, the must-stock list, a few priority metrics, and an exception process in the pilot territories, rolled out as a field campaign on the pilot account set. Watch how long visits really take, check a sample of evidence, run a weekly exception review, and fix the design quickly.Gate: the field workflow is practical, and the action process works.
3

Days 61 to 90: Stabilize and Scale Deliberately

Compare results with the baseline and with similar stores outside the pilot. Review sync timeliness, completeness, and evidence quality. Refine tiers and task lists, set change control for questions, products, campaigns, and metric definitions, and plan a staged expansion.Gate: the evidence supports scaling without multiplying unresolved problems.
Stop signs. Pause expansion if records aren’t syncing reliably, reps can’t complete the workflow within real visit times, denominators are still disputed, or nobody is accountable for exceptions. FieldKo has no standard owner, due date, or closure tracking for exceptions, so agree the exception process (Next Visit To Do’s, incidents, and Flow) before you scale. See Flow Recipes.

Fictional Example

A made-up snack company, Redwood Pantry, pilots in 3 territories with 12 reps and 180 stores, targeting availability of 15 must-stock products.
  • Day 30 baseline: 2,322 of 2,700 checks present, so observed on-shelf availability (OSA) is 86%.
  • Day 45: visits run 12 minutes over plan because the survey has 40 questions. The team cuts it to 18.
  • Day 60 gate: 2,457 of 2,700 present, 91%. Sync Details show 2 reps with repeated failed syncs, which the admin fixes.
  • Day 90 gate: results hold, weekly reviews run without the central analyst, and expansion to 2 more territories is approved.

What to Measure

What to Do When It Goes Wrong

Pilot Checklist

  • Name a sponsor, a program owner, and the pilot region.
  • Write the business objective, baseline metric, and success criteria.
  • Agree the metric dictionary and the must-stock list.
  • Choose representative pilot territories, not only the easiest ones.
  • Run weekly exception reviews from day 31.
  • Record a decision at each gate, and check the stop signs before any expansion.